An industrial client needed a 24-metre clear-span workshop hall — structure that works hard and still looks considered.
Clear span, crane loads, and a budget that forbade waste.
Tapered portal frames optimized bay by bay; connections detailed for site bolting, not site welding.
CHALLENGE
Clear span, crane loads, and a budget that forbade waste.
SOLUTION
Tapered portal frames optimized bay by bay; connections detailed for site bolting, not site welding.
MATERIALS
| MATERIALS | Structural steel S355 · purlins · cladding rails |
|---|---|
| FABRICATION | CNC-profiled plates, SAW-welded frames, full trial assembly. |
| FINISHING | Zinc silicate primer + micaceous iron oxide topcoat. |
| INSTALLATION | Erected in eleven days with bolted connections and surveyed alignment. |
THE RESULT
A working hall with the precision of a showroom.